The long awaited Nursery Pool Bridge rebuilding project got under way on January 2nd. This major engineering project is being assisted by the National Heritage Lottery Fund with a grant of up to £183,500 towards the total cost of around £245,000.
6th January The steel reinforcing rod arrived on schedule today and the longer lengths (18.5 tons in all) were transported to site by rail.
13th January The next two pictures shew the bridge looking South on Sunday 12th with all track removed and the scaffolding complete. Further progress on Monday, this time looking North.
15th January The contractors are proceeding according to plan. As the next picture shows, all the ballast and the old deck have been removed. Work starts today on removing the now redundant cross beams where they are above the main piers. New bearings will now be built onto the existing piers to support the new bridge. As this work begins, starting from the South end of the bridge, shuttering will be placed between the old cross beams. Then work can start on erecting the reinforcing steel.
23rd January The contractors dealing with the reconstruction of Nursery Pool Bridge reported to Trust officials today that they were quietly confident that the contract was on schedule for completion by the March 19th deadline. Despite a run of wet weather things were progressing well. So far the old deck has been removed, the tops of the piers have been excavated ready for the construction of the new concrete plinths on which the main bridge will sit, and the steel erectors have moved in today to start putting the reinforcing steel in place. The old cross beams have been removed where these are intersected by the new concrete plinths on the old piers. Another sub-contractor will begin fixing the shuttering next week in preparation for the main concrete pour. The main concern now is that the weather remains not too unkind. Although the forecast cold snap may not help, the main concern is rain. Not that the amount of water in the River Dart is likely to be a problem as all the work is on the bridge, and not under it, but it is just physically difficult to work in very wet weather.
27th January Work is now in hand on constructing the bridge soffit shuttering. All the piers are excavated ready for the new concrete plinths. The steel reinforcing is fixed in place for the Totnes end abutment and the first two piers from the Totnes end. The steel for the rest and more for the Buckfastleigh end of the bridge will be delivered tomorrow.
3rd February - First Concrete goes in to new bridge! The first concrete ‘pour’ took place today on the reconstruction of Nursery Pool Bridge. All four new pier top plinths and the two end abutments were poured into place today during an operation that took several hours and involved using a radio controlled concrete pump. The weather has been relatively kind with only sporadic rain showers despite other areas of the country receiving drenchings resulting in severe floods.
Work now enters a new phase with the ongoing construction of temporary deck shuttering and installation of many tons of reinforcing bar ready for the main concrete pour to make the new deck. This is scheduled for around February 27th.
11th February 2004 Nice weather and things look to be going well. The woodwork department are just finishing off the deck soffit whilst the steel erectors have got stuck in to setting up the deck reinforcing. The reinforcing for the Totnes end abutment and two piers is done, they are working on the third and have started laying out some of the steel for the actual deck.
17th February The contract for the rebuilding of Nursery Pool Bridge has entered its seventh week. Work continues apace on the setting out of the reinforcing steel for the new deck and the robust kerbs through which the track will be re-laid. If the weather keeps fair it is hoped that the concrete pour for the main deck may be brought forward by a day or so. If this is the case that will be very good news as any extra time available for replacing the track on the new bridge will be very welcome as there is only a short time window before the train service restarts on March 27th.
22nd February The seventh week of the Nursery Pool rebuilding project ended with the erection of the steel reinforcing for the piers and robust curbs all but finished and the project running on schedule. Work will now concentrate on fixing the remainder of the reinforcing steel for the deck before the main concrete pour, timetabled for the end of this week (week eight).
24th February The robust kerb reinforcement is all but complete apart from a few minor details awaiting provision of some critical measurements. The reinforcing for the main deck is now well advanced with the lower level of steel about 2/3rds complete. The main concrete pour to form the deck is now scheduled for this coming Saturday.
27th February Bridge ready for main concrete 'pour'. The steel deck reinforcing and shuttering is now all complete and ready for the main pour of 110 cubic metres of concrete due to start at 8.15am on Saturday 28th February - weather permitting! With an overnight frost expected and cold day forecast with a risk of snow showers, this could throw a 'spanner in the works'. If the day is clear though it should quickly warm up to allow the job to proceed. The photo below was taken at 3.00pm 26th February and shows the contractors doing various final jobs in readiness for the early start. Fingers crossed!!
29th February Bridge pour takes place as planned! Alleluia!! The weather proved fine and not too cold and so the main concrete pour to form the new deck for the bridge took place on schedule yesterday. Work started at 10.00am after the weather had warmed up sufficiently and was complete by 3.00pm. On to the next stage - the robust kerbs.
04th March Following the successful 'pour' of the main deck last Saturday work is now well in hand with preparations for the casting of the first of the robust kerbs. This is scheduled to take place on Monday 8th March. The steel fixers have been busy inserting yet more steel into the kerbs whilst the shuttering experts have been hard at it putting all the formwork in place. One picture shows the special formwork being constructed with plastic faced ply to give a smooth finish. It has to be well anchored down to prevent lifting when the concrete is poured into the structure. The second detail shows a 'Halfen' fixing. These are fitted to the inside of the shuttering and when the shuttering is taken away will have been well and truly cast into the concrete. The uprights for the handrails will be bolted to them.
08th March The first of the robust kerbs was cast at the Nursery Pool Bridge site today. Work will start first thing tomorrow to transfer the shuttering to the downstream side of the bridge ready for a pour at the end of the week.
12th March Bridge ready for final 'pour' With week ten of the Nursery Pool Bridge rebuilding project nearly over the contractors were ready for the final pour of the downstream robust kerb to take place on Saturday March 13th. During the week the shuttering has been removed from the upstream kerb and set up on the second side. The trough through which the trains will run is now readily apparent. The deck will now need waterproofing after which a six inch layer of ballast will be added before the sleepers and rails are laid on top. The running rail height will be 1' 4" below the top of the kerbs.
15th March Nearly there! Week eleven of the contract and the complete bridge has now been cast. The shuttering team are busy removing their handiwork. That should be dealt with by Wednesday when the next operation - deck waterproofing - can begin.
16th March With the shuttering now largely removed the new bridge can be seen for the first time. Now to pray for some dry weather to enable the deck waterproofing to proceed.
17th March Waterproofing under way! The weather was kind today and work is proceeding on the deck water proofing. It will be touch and go whether this process can be completed in the next day or so. It needs to be dry and the weather man is threatening dire conditions coming in during Thursday and for the rest of the week. If the waterproofing can be completed we can proceed with ballasting and track laying and have a chance of opening on time if the concrete has gained enough strength. Fingers crossed!
24th March Ballast Trains use new Bridge With the new version of Nursery Pool Bridge now passed for traffic, albeit with caution as contractors are still carrying out finishing touches and SDR staff are busy fixing the handrails, works trains have been running to and fro all day with ballast to the various winter relaying jobs that await stone and tamping.
Your camera man was out and about to catch some views of these workings on the new structure. The new handrails can be clearly seen - just the uprights at this moment in time. The main contractors are still removing some of the shuttering but much of the safety scaffolding has been removed with just some remaining on each side.
27th March Railway Opens on time! The SDR's 2004 season got off to a fine start on 27th March with the first train over the newly reopened bridge being 0-4-2T No 1420 hauling a rake of three well filled carriages. The railway runs its annual 'Half Price' weekend at the opening weekend every year when many locals and members turn out to enjoy the beauties of a ride along the line. In addition to being able to see the new bridge passengers were able to feel the benefit of the better ride following the winter relaying programme and the recent ballasting and tamping exercises. Some more ballasting needs to be completed along the straight from Nursery Pool Bridge after which the Midland Railway tamping team will bring the track up to scratch. When this work is complete and the handrails fitted to the bridge (only the short length where 1420 is photographed on the bridge has yet been completed) all remaining temporary speed restrictions will be able to be removed, which will be the first time since the line passed into SDR control.
01st April Finishing touches to new Nursery Pool bridge The trackwork on the new bridge is now complete. The Midland Railway tamper and ballast regulator have completed the work on the track both on the bridge and on each side where the alignment has been altered following the centring of the track on the bridge after 112 years! The Midland Railway ballast regulator is seen putting the final touches to the track on the bridge and their tamping machine dealing with the straight just South of the bridge. If you need your line tamping and you don't have your own machine then the SDR would thoroughly recommend you consider seeking their services.
28th April Nursery Pool project virtually complete The handrail stanchions have now been fitted to Nursery Pool Bridge, which only leaves a section of walkway on each side and the finishing of the painting of the old structure for the project to be completed. Cast signs are also being made to add to the bridge as a finishing touch. The wording will be 'South Devon Railway - 2004' in the style of the Great Western 'rounder' combined name and numberplates that were fitted to many of the early Great Western 4-4-0's.
© South Devon Railway Trust 2004